General Motors Spring Hill Expansion

IMN Building Expansion

General Motors Spring Hill Expansion - Steel Fabrication & Erection - Aristeo Construction  - DJI_0306_cropped

Spring Hill, TN

Delivery Method: Design Build

Project Value: $9,500,000

  • 58,000 sq ft addition to the largest GM facility in the United States
  • 625 tons of structural steel
  • 2,300 cubic yards of concrete
  • Use of the addition’s footprint as a laydown, where none was available
  • Plant access roads remained open
  • Added coordination working adjacent to UAW cafeteria and production aisles

Location: Canton, Mississippi
Owner: Nissan North America
Project Value: $2,000,000
 

Paint Shop Mezzanines

Location: Louisville, Kentucky
Owner: Ford Motor Company
Project Value: $4,000,000
 

Paint Booth Steel

Location: Pontiac, MI
Owner: General Motors Corporation
Project Value: $2,100,000

Pontiac Stamping Tryout Press Pit

Location: Pontiac, MI
Owner: General Motors Corporation
Project Value: $3,033,000

Pontiac Fuel Cell Lab Expansion

Location: Bedford, IN
Owner: General Motors
Project Value: $6,000,000
 

Die Cast Machine Steel

Location: Dearborn, Michigan
Owner: Ford Motor Company
Project Value: $8,000,000
 

Operating Floor Steel

Location: Detroit, Michigan
Owner: EWI Worldwide
Project Value: $1,000,000

NAIAS Exhibit, Steel Framing

Location: Detroit, Michigan
Owner: Detroit Entertainment LLC
Project Value: $11,000,000
 

Facade Replacement

Location: Detroit, Michigan
Owner: Detroit Building Authority
Project Value: $3,500,000
 

Headquarters Building Restoration
One of the main reasons we continue to hold your company as one of our preferred long term partners is your ability to understand our needs and deliver on your promises with the appropriate sense of urgency. Ford Motor Company