The scope of work included all labor and materials for the installation of approximately 1,000 LF of utility tunnels ranging from 12 FT to 17 FT deep and coordination of all mechanical, electrical, and building maintenance systems (BMS) inside the new tunnels and existing buildings.

Aristeo’s Steel Division provided and installed miscellaneous steel supports, access hatches, and unique tunnel platforms with ladders.

Throughout the six month duration, Aristeo avoided interference with campus activities, transportation and pedestrian pathways, buildings, and facilities.