D219_258 Program Chicago Assembly Plant
This text is replaced by the Flash movie.
Aristeo Construction served as the design/build contractor for multiple elements of the D219/258 Program at Ford Motor Company's Chicago Assembly Plant. Aristeo performed all planning, scheduling, subcontract bidding/award, and field supervision for this major plant renovation. All construction activities required careful coordination with plant personnel to maintain the schedules without interrupting ongoing plant operations. The unique challenges faced on site included safety, labor, site logistics/aged structure, an aggressive schedule, and production constraints.
Project Highlights
-
D219/258 Body Shop
-
Torrence Avenue Rework
-
Process Ventilation System Installation
-
New Roll Test Installation
-
Mezzanine Installation
-
Glass Cells & Retaining Wall
-
Engine Stuffer Pits
-
RTO Platform 2-Strand Conveyor
-
Remove Armadillo Plate
-
Cross Transfer Pits
-
Penthouse Modifications
-
Shuttle Car Transfers
-
Staubli Robot Installation
Project Name
D219/258 Program Chicago Assembly Plant
Chicago, Illinois
Owner
Ford Motor Company Vehicle Operations
17000 Oakwood Boulevard
Dearborn, MI 48121
Contact
Frank Schiavi
Project Value
$55,300,000
Delivery Method
Design/Build General Contractor
Year Completed
2004