Chrysler 3.5L Engine Program
This text is replaced by the Flash movie.
Aristeo Construction completed the extensive site preparation, flumes and foundations packages at Chrysler's Kenosha Engine Plant. Site preparation for this new plant included excavation, sheeting, storm sewers, fire protection water lines, storm water interceptor pits and on-site paving. We placed more than 12,000 cubic yards of concrete in the filter gallery, head line, crank line and engine assembly areas. Project highlights include:
- 350,000 FT2 of trap rock floors and wet decks
- 3,000 lineal feet of flume
- 2,000 feet of trenches & 2 sizeable filter pits
Project Name
2003 MY 3.5L Engine Program
Kenosha Engine Plant
Kenosha, Wisconsin
Owner
Chrysler LLC
800 Chrysler Drive
Auburn Hills, MI 48326
Construction Manager
Graycor Industrial Constructors
2711 60th Avenue
Kenosha, WI 53140
Project Value
$15,000,000
Delivery Method
Concrete Contractor
Project Size
500,000 FT2
Year Completed
2001
Architect/Engineer
Albert Kahn Associates
| << Previous | | | Next >> |