Chrysler 2.7L Engine Program


Aristeo Construction served as the concrete contractor on the 2.7L Engine Site Prep Program at Chrysler’s Kenosha Engine Plant. The project consisted of the complete site preparation for the new engine line. We performed this project on a compressed four month schedule working two shifts, seven days per week.

Aristeo self-performed all site prep work which included the following:

  • 3,000 lineal feet of flumes
  • 8 large coolant pits
  • 200,000 FT2 of new plant floor
  • 50 machine and CMM foundations
 

Project Name

2.7L Engine Site Prep Program
Kenosha Engine Plant
Kenosha, Wisconsin

 

Owner

Chrysler LLC
800 Chrysler Drive
Auburn Hills, MI 48326 

 

Contact

Jim Abbott

 

Project Value

$5,200,000

 

Delivery Method

Concrete Contractor

 

Year Completed

 1997 

 

Architect/Engineer

Quality Engineering Corporation

 

 