Noble Environmental – Wind Parks

Project Description

Aristeo’s role included access road construction and pouring base foundations and pads for a total of 188 wind turbines to produce nearly 1,000 megawatts.

Our first project in Bliss, New York included constructing roads and base foundations. Pouring an average of 330 yards of concrete per day and placing nearly 9400 anchor bolts, we completed 67 tower foundations within our projected schedule.

The other two Noble projects were located in upstate New York in the towns of Clinton and Ellenburg. We poured 700 yards of concrete daily to complete 121 foundations on a fast track schedule. Our rigging crew followed close behind to erect these 1.5 megawatt turbines. We were proud to play a major role in the construction of these wind parks.